Standing to bring a procurement case


11th October 2023

The High Court recently handed down its judgment in IGT v The Gambling Commission & Allwyn Entertainment, which concerned the definition of an “economic operator” and in particular, who has standing to pursue a claim against a contracting authority under The Concession Contracts Regulations 2016. The principles established in this case are also likely to apply equally to procurements proceeding via the Public Contracts Regulations 2015.

Following a preliminary hearing, the High Court held that the procurement legislation would only entitle those entities who would be seeking to obtain a public contract with a cause of action to bring a claim (that is bidders or potential bidders).

The case concerned an incumbent provider, Camelot, commencing Court proceedings against the Gambling Commission following the latter’s decision to award a new contract to Allwyn. IGT, Camelot’s sub-contractor, also commenced its own proceedings along similar grounds to those advanced by Camelot.

Following Allwyn purchasing Camelot, Camelot discontinued its claim against Allwyn; however, IGT continued with its claim alone. As a result, the Court had to determine, as a preliminary issue, whether IGT had standing (i.e. the legal right) to bring its challenge as a sub-contractor when it was not the primary bidder.

IGT was unsuccessful on this preliminary issue and the claim was accordingly dismissed. In particular, the Court noted the following:

On the wording of Article 1(3) of the Remedies Directive, an entity who did not seek to obtain the contract (i.e. a bidder) will generally not have the necessary standing to challenge the result of the procurement. That is the straightforward reading of the words…..

As a result of IGT having lost its challenge, it was required to pay some of the Gambling Commission’s costs; however, the situation was not as clear when it came to IGT having to pay Allwyn’s costs.

At a further hearing, the High Court held that the successful bidder, Allwyn, was entitled to recover its costs against IGT on the following basis:

  • Allwyn clearly had a separate interest justifying its participation and had participated substantively;
  • The value and public importance of the litigation was significant;
  • At an early stage, IGT had sought a costs order against Allwyn.

The High Court’s judgment re-affirms previous judgments and has confirmed that an economic operator has to be in it to win it when it comes to pursuing a procurement case against a contracting authority.

Blake Morgan has significant expertise in pursuing and defending contentious procurement matters. If you have any questions regarding this decision on standing to bring a procurement case or procurement law generally, or have any procurement issues, please get in touch with our experts who shall be pleased to help.

Public procurement specialists

Speak to one of our experts

Arrange a call

Enjoy That? You Might Like These:


articles

1 November -
As many of us may know already, local authorities that run their own leisure facilities have, since March 2023, had some very good news from Government, confirming that leisure services... Read More

case-studies

30 October -
The Vice President of the Court of Protection has issued guidance in the case Leicestershire County Council v P and Anor [2024] EWCOP 53 relating to fluctuating capacity, when anticipatory... Read More

events

28 October
Our Public Sector Insights webinar on Thursday 12 December focused on data protection and information governance. Read More